At Safvero, in-stock products ship within 7 days, customization of in-stock products is completed within 15 days, and full customization follows a 25-day schedule. The schedule runs from an approved specification, so late artwork, open color decisions, extra sample rounds and changes after approval are what usually move delivery. Transit to the destination comes on top, and sample arrangements are confirmed separately for each project.
Lead time by route
Confirm the route first. It sets the schedule more than any other decision.
| Route | Lead time | Typical scope |
|---|---|---|
| In-stock product | Ships within 7 days | Existing style, no changes |
| In-stock customization | Within 15 days | Branding added to stock |
| Full customization | 25-day schedule | New fabric, color, construction |
| Samples | Confirmed per project | Agreed through the inquiry |
When does the schedule start?
Production schedules run from an approved, available specification, not from the first inquiry. Before that point, the brief, quotation, material choices, artwork and any sample rounds have to be settled. The faster those decisions close, the sooner the schedule starts. Treat specification approval as a milestone with a date and a named owner on both sides.
What moves the start date?
Most delays happen before production, while decisions are still open.
- Artwork arriving late or in the wrong format.
- Open decisions on color, fabric or tape.
- Extra sample rounds after unclear comments.
- Changes after approval, which reopen the specification.
- Custom materials that must be sourced before cutting.
- Label or packing details confirmed late.
Materials and their effect
Standard fabrics, tape and trims that are already available keep an order on the shorter routes. A custom-dyed fabric, special tape or non-standard zipper must be produced or sourced before cutting begins, which is one reason full customization follows a longer schedule than customization of in-stock products. Ask early which materials in your specification are standard and which are custom.
Samples and pre-production samples
Sample and pre-production sample arrangements depend on the product and the project requirements and are confirmed case by case through an inquiry. Plan them into the timeline, because each sample round adds review time on both sides. Consolidated comments, a frozen specification revision and a named approver usually mean fewer rounds and an earlier start.
Map the full-custom sequence
A fully customized order typically moves from brief and quotation to specification and artwork approval, sample and revisions, bulk production, inspection and packing, and then transit. Each step depends on the one before it. When one approval arrives late, every later step moves with it, so build buffer around the approvals rather than around production alone.
Working to a fixed delivery date
If the goods must arrive by a fixed date, say so in the first message and plan backward from it: transit, production on the applicable route, sample review and approvals. Where the date leaves no room for a sample round, an in-stock style or customization of an in-stock product follows the 7-day or 15-day route. State which details may change to protect the date, such as using an existing color instead of a custom one.
Plan transit separately
Production lead time ends when goods are ready to ship. Transit by sea, air or courier comes on top, along with customs clearance at the destination. Share the delivery destination and the required on-site date with the inquiry so the production route and shipping method can be planned together. Repeat orders with an unchanged specification are usually more straightforward to schedule, but availability still needs confirmation.
Schedule checklist
Agree these points before the order is confirmed.
- The order route: in-stock, in-stock customization or full customization.
- The approval date for the specification and artwork.
- The sample route and the number of review rounds planned.
- Any custom materials and when they must be confirmed.
- Delivery destination, shipping method and required on-site date.
Common questions
How long does custom workwear production take?
At Safvero, full customization follows a 25-day schedule, customization of in-stock products is completed within 15 days, and in-stock products ship within 7 days. The schedule runs from an approved specification; samples and transit are planned separately.
Why do lead times change after an order is placed?
Usually because the specification changes after approval, artwork or approvals arrive late, or a custom material has to be sourced. Each reopens part of the schedule. Freezing the specification and approving it in one consolidated round keeps delivery predictable.
Are samples included in the production lead time?
Sample and pre-production sample arrangements are confirmed separately for each project through an inquiry. Plan the sample rounds before the production schedule starts, because bulk production runs from the approved specification.
Are repeat workwear orders faster?
They can be more straightforward when the specification, materials and approvals stay unchanged, because the decisions are already made. Availability and scheduling still need confirmation for each order.